Placing arrays in cells with Excel VBA - excel

I use the following Excel custom function to put a value into cell based on a start and end date, and a frequency. The spreadsheet is for projecting costs into the future, so I may allocate $10k every 5 years starting from 2022 and ending in 2072 (eg 2022, 2027, 2032....2067, 2072). I also index it also sometimes.
Current Macro
Public Function spend(FY, start, finish, frequency, amount, index, base)
'Check if FY is within range if not return nothing and exit
If FY < start Or FY > finish Then
spend = ""
Exit Function
End If
'Check frequency to see if valid year
If FY = start Then
spend = amount * (1 + index) ^ (FY - base)
ElseIf (FY - start) Mod frequency = 0 Then
spend = amount * (1 + index) ^ (FY - base)
Else
spend = ""
End If
End Function
Current Spreadsheet
For some larger projects, the costs may spread over multiple years (eg Year 1:$100k, Year 2:$500k, Year 3:$600). Is there a way to put a series of numbers into "Amount" cell. For example if this project repeats every 10 years from 2022 simliar to below:

Related

Trying to show a full years amount based on a smaller fraction of the year's total

this is my first post.
Right now, I have a limited set of data ranging from the beginning of this financial year until now. I'm trying to show what a full year's worth of that data would look like.
For example, if the number is at 10, and the data range is from 1/07/2021 - 30/12/2021 (half the year), then the end output should be 20. Or for example, turn a 12 with 3/4 of the year date range to 16 for a full years' worth.
However, my current formula would end up with 15 (10 + "half") rather than (10 + 10)
Right now this is what I have, but I know there's something off on my logic, as the output is smaller than it should be:
D1+((364-(F1-E1))/365)*D1
where E1 is the start date and F1 is the end date, and d1 is the number for that date range
Thanks in advance
endDate - startDate will give you the number of days the data covers.
(endDate - startDate) / 365 will give you what fraction of a year the sample represents.
Let’s say this works out to be 30%, or 0.30.
annualValue * 0.30 = periodValue and therefore we know that periodValue / 0.30 = annualValue.
So there it is, the cell you want the Annual Value in should be:
= periodValue / ( ( endDate - startDate) / 365 )
I will leave it to you to replace each of the three named values in my example to be the correct cell references. I suspect that’s probably:
=D1/((F1-E1)/365) which is the same as (D1*365)/(F1-E1).
The easy way to remember this is that it’s just cross-multiplication.
periodValue / days is proportionate to annualValue / 365. Thus periodValue / days = annualValue / 365. Cross-multiply and you get periodValue * 365 = annualValue * days. Divide both sides by days and you get `annualValue = (periodValue * 365)/days.

How to get the Week of the month (1:6)

We can find different approaches to determining the week of the month, and even though there are many pages on 1:4 and/or 1:5, there is very few around 1:6 approach.
So to give you a bit of the context, I am working with a pivot table in Excel which gets its values from a Power Query source.
In Power Query, there is a function Date.WeekOfMonth which takes in the date and returns a number between 1 and 6.
In this definition, weeks start from Sunday and ends on Saturday.
So, for example, the first two days of October 2021 -i.e. Fri & Sat- fall in the 1st week of Oct, while the 3rd day of Oct 2021 starts the second week, and then the last day of October 2021,i.e. Oct 31, is the only day in the 6th week.
I had an automation task on hand in which I needed to pull data from the Power Query-generated pivot, so I had to implement a piece of code in VBA which calcs weeks the same.
Unfortunately, I couldn't find any prepared snippet, so after implementing I though it might worth sharing.
(Any comments and suggestions appreciated)
The DatePart function is perfect for this. Using DatePart with the interval set to "weeks" you can find the week of a given date. Then you subtract the number of weeks before the first day of that month (which sets the first day to week = 1).
Function WeekNumOfDate(D As Date) As Integer
WeekNumOfDate = DatePart("ww", D) - DatePart("ww", DateSerial(Year(D), Month(D), 1)) + 1
End Function
Here is a second version of the function that has the ability to set the FirstDayOfWeek argument:
Function WeekNumOfDate(D As Date, Optional FirstDayOfWeek As VbDayOfWeek = vbSunday) As Integer
WeekNumOfDate = DatePart("ww", D, FirstDayOfWeek) - DatePart("ww", DateSerial(Year(D), Month(D), 1), FirstDayOfWeek) + 1
End Function
As an example for using FirstDayOfWeek: With FirstDayOfWeek set to vbThursday, the date "Nov 5th, 2021" will return as Week 2, whereas it would by default be counted as Week 1. November 1st to 3rd of 2021 will be week 1, and then 4th to 10th will be week 2.
Its implementation in VBA is:
Function WeekOfMonth(My_Date As Date)
If Day(My_Date) > Day(My_Date - 1) And Weekday(My_Date) > Weekday(My_Date - 1) Then
WeekOfMonth = WeekOfMonth(My_Date - 1)
ElseIf Day(My_Date) > Day(My_Date - 1) And Weekday(My_Date) < Weekday(My_Date - 1) Then
WeekOfMonth = WeekOfMonth(My_Date - 1) + 1
Else
WeekOfMonth = 1
End If
End Function
Note that even though the above function is recursive, its time and space complexity is an expression of order N, which here cannot exceed 31.

Divide revenue across quarters in two years - Excel and SmartSheet

I need a formula to:
recognize the quarter for each date
divide the revenue in half for the start and end quarter.
Below is an example of the results I'm looking for. Need this to be a formula I can build in SmartSheet and/or Excel and transfer over to a SmartSheet.
Add a "helper row" with quarter number and year so you can use a SUMIFS/2
=(SUMIFS($[Est Revenue]#row, $[Start Date]#row, IFERROR((ROUNDUP(MONTH(#cell) / 3) + "" + YEAR(#cell)), 0) = [Q1 2020]$1) + SUMIFS($[Est Revenue]#row, $[End Date]#row, IFERROR((ROUNDUP(MONTH(#cell) / 3) + "" + YEAR(#cell)), 0) = [Q1 2020]$1)) / 2
The helper row would be quarter number before the 4 digit year. So 12020 would be quarter 1 2020.

How can i only select the parameters corresponding to each month automatically?

I have a table that includes data from two entire years, and i need to calculate the notification rate month by month in those two years. Because of that, i want to do the calculation with the data corresponding to one month.
In the example below i want to obtain the number of times a certain velocity appears in each month, so for example: if I select 1M/s, for January of 2017 the program should return 2, and 0 for the other months.
I have obtained the result for 1 month, but i want to change the start and finish of the counter each time the month changes automatically
numero1 = 1
numero2 = 1
parametro = ActiveWorkbook.Sheets("Hoja4").Cells(4, 3)
'Velocidad
If parametro = ("Velocidad") Then
archivoConsulta = ActiveWorkbook.Sheets("Hoja4").Cells(4, 4)
**For cont1 = 4 To 32**
parametro_avi = Sheets("hoja1").Cells(cont1, 56)
If parametro_avi = archivoConsulta Then
numero1 = numero1 + 1
End If
Next cont1

Get day number within calendar week for a specific date

I have a data set which includes dates.
I need to split this out by week number for reporting purposes.
What I have so far is:
startDate variable containing 03/01/2015 (populated from data in spreadsheet)
startDay = Day(startDate)
startMonth = Month(startDate)
startYear = Year(startDate)
startWeek = Application.WorksheetFunction.WeekNum(DateSerial(startYear, startMonth, startDay))
which gives me week 1 in startWeek
However I know need to know how far into week 1 the date is.
So for this example, as the date is the 3rd of January, it includes 3 days of week 1
Meaning the reporting I'm putting together will only report on 3 days (as opposed to the full week)
The only way I've figured to do this so far is to calculate which day of the year the date is and the use a MOD calculation (basically divide by 7 and the remainder is how far into the week it is)
dayNumber = DateDiff("d", DateSerial(startYear, 1, 1), DateSerial(startYear, startMonth, startDay)) + 1
dayOfWeek = dayNumber Mod 7
This does work, but I was wondering if there was a nicer solution than this.
You could use a loop to determine how many days before startDate the week number changed:
Public Sub FindDaysInWeekNo()
Dim startDate As Date
startDate = DateSerial(2015, 1, 3)
Dim startWeek As Integer
startWeek = Application.WorksheetFunction.WeekNum(startDate)
Dim i As Integer
Do While startWeek = Application.WorksheetFunction.WeekNum(DateAdd("d", -i, startDate))
i = i + 1
Loop
Debug.Print i '= 3rd day in this week number
End Sub
The following table shows my comparison to the other suggested formulas and why I think that (refered to =WEEKNUM) my calculation is correct.
Note that if you assume 1st to 7th January will be week 1 (days 1 to 7) you cannot use the WeekNum function because this will give you a different result (see table above and note that the first week has only 6 days according to the WeekNum function). Also you cannot name this week number (as what everybody calls week number is defined as https://en.wikipedia.org/wiki/Week#Week_numbering).
Instead you will need to use …
Public Function AlternativeWeekNum(startDate As Date) As Integer
AlternativeWeekNum = WorksheetFunction.Days(startDate, DateSerial(Year(startDate), 1, 1)) \ 7 + 1 'note that this no normal division but a integer division and uses a backslash instead
End Function
to calculate the week number your alternative way, and …
Public Function AlternativeWeekNumDay(startDate As Date) As Integer
AlternativeWeekNumDay = WorksheetFunction.Days(startDate, DateSerial(Year(startDate), 1, 1)) Mod 7 + 1
End Function
to calculate the day in the alternative week.
You can use the Weekday() function for this:
=WEEKDAY(B4;2)
The second parameter mentions how you want your days to be counted (starting from Sunday or Monday, counting starting from 0 or from 1, ...).
dayOfWeek = (8 + Weekday(startDate) - Weekday(DateSerial(startYear, 1, 1))) mod 7
Just take the positive mod 7 of the difference between the current Day-Of-Week and the Day-Of-Week for the 1st January of whatever the year is