I have the following data.
Available resources data per day:
A
B
C
D
E
F
G
H
I
J
K
L
M
N
2
resources
day
3
1
2
3
4
5
6
7
8
9
10
11
12
4
empl.1
8
8
4
2
2
4
4
8
8
5
empl.2
8
4
4
8
4
8
6
empl.3
And different products and it's production per hour (per employee) and the required quantity per part:
P
Q
R
S
2
product
production/hour
required qty
3
4
prod.1
1
60
5
prod.2
1
6
6
prod.3
2
4
From this data I want to calculate the number of products that can be produced per day based on the available employees for the day and the production capacity for that product up until the goal is reached for that product.
edit: calculation from original post was calculating to hours spent per product per day only, not to qty of products produced; also the MOD-part gave wrong calculation results if the daily produced qty exceeds the goal
I use the following formula to calculate the above (used in C11 and dragged to the right):
=LET(
prod,BYROW($B11:B13,LAMBDA(r,SUM(r))),
reached,--(prod<$S$4:$S$6),
dayprod,IFERROR(SUM(C4:C6)/SUM(reached*$R$4:$R$6),0)*reached*$R$4:$R$6,
IF(prod+dayprod>$S$4:$S$6,dayprod-((prod+dayprod)-$S$4:$S$6),dayprod))
This results in the following:
A
B
C
D
E
F
G
H
I
J
K
L
M
N
9
product
day
10
1
2
3
4
5
6
7
8
9
10
11
12
11
prod.1
2
8
4
6
2
8
4
0
8
12
6
0
12
prod.2
2
4
0
0
0
0
0
0
0
0
0
0
13
prod.3
4
0
0
0
0
0
0
0
0
0
0
0
This formula sums the hours from the employees available that day and divides their hours over the products that did not reach the goal yet.
If the goal is reached the available hours are divided over the remaining products to produce.
Screenshot of the data + current result:
Now the problem I'm having is the following:
If the goal is reached for a product somewhere halfway the day the dayprod-((prod+dayprod)-$S$4:$S$6)-part of the function calculates the remaining hours of production for that product for that day, but the available hours from the employees are divided over each product that needs production still, but let's take the following example:
prod.1, day 2: value 8
prod.2, day 2: value 4
The 8 for prod.1 is calculated based on both prod.1 & prod.2 in need for production still and both take 1 hour per person to produce one.
Having 16 hours available that day that means a capacity of 8 for each.
But the challenge lies in the goal being reached halfway the day.
In fact the first 4 hours are used by both employees to produce 4 of each product.
The last 4 hours both employees can focus on prod.1 resulting in not qty 4 of production for the last 4 hours, but 4 + 4 which results in a total of 12 being produced for prod.1, not 8 like now calculated.
How can I get the formula to add the remaining time to the remaining products?
Original post, prior to edit, containing error (not calculating to number of products, but to number of hours spent per product per day only)
I use the following formula to calculate the above (used in C11 and dragged to the right):
=LET(
prod,BYROW($B11:B13,LAMBDA(r,SUM(r))),
reached,--(prod<$S$4:$S$6),
dayprod,IFERROR(SUM(C4:C6)/SUM(reached*$R$4:$R$6),0)*reached*$R$4:$R$6,
IF(prod+dayprod>$S$4:$S$6,dayprod-MOD(prod+dayprod,$S$4:$S$6),dayprod))
This results in the following:
A
B
C
D
E
F
G
H
I
J
K
L
M
N
9
product
day
10
1
2
3
4
5
6
7
8
9
10
11
12
11
prod.1
2
8
4
6
2
8
4
0
8
12
6
0
12
prod.2
2
4
0
0
0
0
0
0
0
0
0
0
13
prod.3
4
0
0
0
0
0
0
0
0
0
0
0
This formula sums the hours from the employees available that day and divides their hours over the products that did not reach the goal yet.
If the goal is reached the available hours are divided over the remaining products to produce.
Screenshot of the data + current result:
Now the problem I'm having is the following:
If the goal is reached for a product somewhere halfway the day the MOD-part of the function calculates the remaining qty for that product for that day, but the available hours from the employees are divided over each product that needs production still, but let's take the following example:
prod.1, day 2: value 8
prod.2, day 2: value 4
The 8 for prod.1 is calculated based on both prod.1 & prod.2 in need for production still and both take 1 hour per person to produce one.
Having 16 hours available that day that means a capacity of 8 for each.
But the challenge lies in the goal being reached halfway the day.
In fact the first 4 hours are used by both employees to produce 4 of each product.
The last 4 hours both employees can focus on prod.1 resulting in a total of 12 being produced for prod.1, not 8.
I kind of broke my head on getting this far, but from here I could use some help.
How can I get the MOD part of the formula to add the remaining time to the remaining products?
I was able to find a solution to my problem.
I had to use the result from the formula in place and check if the sum up to the current day (including that day's production) exceeds the goal. If so I needed to get the time difference between the day's production and that day's production needed to get to the goal. The difference is the time of production to be added to the remaining part(s) for that day that did not reach the goal yet, also not when adding the day's production.
This results in the following formula in C11 dragged to the right:
=LET(
prod,BYROW($B11:B13,LAMBDA(r,SUM(r))),
prodhour,$R$4:$R$6,
goal,$S$4:$S$6,
reached,--(prod<goal),
dayprod,(IFERROR(SUM(C$4:C$6)/SUM(reached*prodhour),0)*reached*prodhour)*prodhour,
preres,IF(prod+dayprod>goal,dayprod-((prod+dayprod)-goal),dayprod),
timecorr,(dayprod*(dayprod<>preres)-preres*(dayprod<>preres))/prodhour,
reachedcorr,reached*(timecorr=0),
dayprodcorr,(IFERROR(SUM(timecorr)/SUM(reachedcorr*prodhour),0)*reachedcorr*prodhour)*prodhour,
IF(prod+dayprod>=goal,dayprod-((prod+dayprod)-goal),dayprod+dayprodcorr))
Where preres is the previous result (from where I got stuck in the opening post).
And the corr parts are taking care of the correction if goal is reached for a product and there was still production time remaining.
Related
Got a bit of a conundrum I've been wracking my brain on for far to long and was wondering if anyone could help.
I have a list of items in column A and columns labelled as weekly periods from B:DA
Item Code
Week 1
Week 2
Week 3
Week 4
Week 5
Week 6
Week 7
Week 8
Results
Item 1
1
1
0
1
0
0
1
0
3
Item 2
1
1
0
0
1
1
1
I need to count the number of times the weekly status goes from 1 to 0 but not from 0 to 1.
In the tabled example I would expect the results to be Item 1 = 3 and Item 2 = 1
Any help pointing me in the right direction would be much appreciated!
Use COUNTIFS():
=COUNTIFS(B2:CZ2,1,C2:DA2,0)
The offset ranges will allow the count of when the prior cell is 1 and the following is 0.
In Microsoft Excel, I have a named (2D) range. For simplicity, let's assume it looks like this:
1
2
3
4
5
5
4
3
2
1
This represent a time series growth curve, where N number of these could kick off in any point in time. I'm looking for an efficient way to calculate what the cumulative sum of these at any point in time would be, given that N start at that point in time.
So for example, if one starts at time 0, and one at time 3, and two at time 7:
0
1
2
3
4
5
6
7
8
9
1
0
0
1
0
0
0
2
0
0
Then the cumulative total would be:
0
1
2
3
4
5
6
7
8
9
1
2
3
4
5
5
4
3
2
1
1
2
3
4
5
5
4
2
4
6
---
---
---
---
---
---
---
---
---
---
1
2
3
5
7
8
8
10
11
11
I'd like to write a formula that gets to that total without having to use those extra rows to sum over, but can't figure out how.
Use SUMPRODUCT and INDEX:
=SUMPRODUCT(INDEX($M$1:$V$1,(COLUMN()-COLUMN($A$1:A1)+1)),$A$2:A2)
The ranges are dynamic and increase as it is pulled over.
with versions that are not Office 365 we need to trick INDEX into accepting an array:
=SUMPRODUCT(INDEX($M$1:$V$1,N(IF({1},(COLUMN()-COLUMN($A$1:A1)+1)))),$A$2:A2)
This would then be confirmed with Ctrl-Shift-Enter to make it an array formula.
In excel I have a dataset. This represents how much stock of 2 products is sold in the first, second, third, etc... month of the product being on the shelves (starts in A1):
Month 1 2 3 4 5 6 7 8 9 10 11 12
Product 1 3 5 2 1 6 1 2 4 7 2 1 5
Product 2 2 1 5 6 2 8 2 1 2 3 4 9
However, the first product sales do not always occur in month 1. They occur in month X. Is there a way (not VBA or copy and paste) of shifting the entries right by 'x' so they align with the month.
Example for data above
Product 1 starts in month 2
Product 2 starts in month 5
Month 1 2 3 4 5 6 7 8 9 10 11 12
Product 1 0 3 5 2 1 6 1 2 4 7 2 1 5
Product 2 0 0 0 0 2 1 5 6 2 8 2 1 2 3 4 9
*0 not required (great if possible), but more for illustration
Thanks
I have created a simple example that does the same job. The shown formula is copied over the shown cells in the row of new data. (The number '2' in the formula refers to the column number of the starting data cell which is column B, hence 2.)
I need to produce a total value for each month of the year from a generated report. Data is split into colunms one with a value you the other with a date.
I need to return a total for each month.
Data is output as such:
100 21/01/2019
200 21/06/2019
150 01/01/2019
300 14/09/2019
8 08/05/2019
I need it to return as
1 2 3 4 5 6 7 8 9 10 11 12
250 0 0 0 8 200 0 0 300 0 0 0
With a further column for the following year. The original data and dates can be removed as this can be reproduced when running the next report.
You could try the below:
Add a helper column next to you date to get the month of the date:
=MONTH(B3)
and use:
=SUMPRODUCT(($C$3:$C$7=F2)*($A$3:$A$7))
Results:
I am trying to create a resource calculator that can tell me how many people i need to put on each section depending on the current work waiting and work coming in. Prioritizing sections which have the most work waiting first.
Upper Limit Allocation Prod Ranking
12 [to calc] 28% 1
15 18% 2
5 17% 3
4 8% 4
2 6% 5
3 .2% 6
4 .2% 6
Similar to the other question I have a constraint that i only have so much to allocate. For this example we will use 38 as the amount that is to be allocated.
I have used the formula from the other answer:
=MIN(A2,$E$1-SUMIF($D$2:$D$8,"<"&D2,$B$2:$B$8))
Where E1 contains the total to be allocated.
I have two issues with this formula:
1)The issue that I am having is that I require a minimum value of atleast 1 person in each of these sections.
I have tried using a max function to simply set this value, however this leads to the resources allocated going over the total amount.
What equation would I need to use to make it account for both the total available to allocate, the minimum requirement for each fund and the maximum limit for each fund.
2) It only returns solid integers, would there be a way to retreive more precise results, maybe by changing it to a % distribution?
UL Alloc Rank Capacity Lower Limit
2 1 15 93 1
3 1 15
4 1 15
6 6 8
1 1 15
2 1 15
4 4 9
2 2 7
4 4 4
15 15 2
12 12 10
12 12 1
1 1 11
13 13 5
6 6 6
5 1 15
5 5 3
1 1 14
2 2 13
3 3 12
3 1 15
Reference: Using the Excel's Rank() function to calculate allocations based on ranking and constraints
Simply subtract the 100 on all sides and add them separately:
=MIN(A2-100,($E$1-100*COUNTA($A$2:$A$8))-(SUMIF($D$2:$D$8,"<"&D2,$B$2:$B$8)-COUNTIF($D$2:$D$8,"<"&D2)*100))+100
What is returned depends on your entries in Column A and in E1. You can change Column A based on a percentage distribution and the formula will return the corresponding values.
Edit:
If you set your lower threshold into F2, your Constraint into E2, using this formula
=MIN(A2-$F$2,($E$2-$F$2*COUNTA($A$2:$A$8))-(SUMIF($D$2:$D$8,"<"&D2,$B$2:$B$8)-COUNTIF($D$2:$D$8,"<"&D2)*$F$2))+$F$2
the result looks like this: