Going from Scrum to Kanban near "release" [closed] - agile

Closed. This question needs to be more focused. It is not currently accepting answers.
Want to improve this question? Update the question so it focuses on one problem only by editing this post.
Closed 5 years ago.
Improve this question
I am working as Scrum Master on a large software project. We are currently running Scrum.
We have about one month left in the development phase before we are supposed to end our implementation phase.
I am strongly considering switching to Kanban (Or GTD) for the last couple of weeks due to:
We have an absolute deadline
It is very hard to plan two (or one) week ahead now that we are this close to the end. The agenda, priority and outstanding tasks changes almost each day. We daily find new tasks we must remember to do before we can say our development phase is finished.
Kanban let me easier identfiy which tasks are waiting for reponse, which tasks are waiting for verification etc.
Anybody have experiences with this? Is this a good idea?
Our sprints are not entirely pontensial shippable increments (I know they should have been, but thats not what I want to discuss here)

Even though I can be considered a Kanban proponent I would think twice before making such move.
On one side:
Kanban deals very neatly with rapidly changing task priorities. It is a good answer for environments where classic time-boxed approach, here: Scrum, doesn't work very well.
Introducing simple Kanban system doesn't require much effort.
Kanban itself isn't an approach to software development and/or project management and should be put on the top of something. However, it seems that you already have this "something" as, at the moment, you have your project organized.
On the other hand:
Adding new tool to your toolbox always adds some hassle and, since you are at the end of the project, it may not be such a good idea to add the hassle now.
Kanban, as pretty much any other tool, will give you value if and only if you get team buy-in before introducing it. I mean Kanban board is useless unless it is updated by everyone in the team regularly.
If you are fluent with what you do, namely following Scrum, resigning from a part of it, namely time-boxing, may have a negative impact on team's productivity. At the same time it'll take some time before you get familiar with a new method, so there can be a question when you're going to get value of switching to other method.
All in all, I would definitely consider Kanban to such work as it gives you pretty good visibility and high flexibility in a situation where priorities are changing all the time. However, I wouldn't say that, in your case, it is a sure-shot decision. If you planned for it in a bit longer perspective it would be a no-brainer to try Kanban.
Personally, I'd probably try anyway and treat it as an experiment. If it works you keep doing it. If it doesn't you retreat back to what you are good at and eventually try Kanban in another project with a bit more preparation.

Related

Scrum Taskboard - can the tasks change? [closed]

Closed. This question does not meet Stack Overflow guidelines. It is not currently accepting answers.
This question does not appear to be about programming within the scope defined in the help center.
Closed 5 years ago.
Improve this question
The company I work for is currently looking to move from traditional waterfall into Scrum for development. We are in the process of slowly adopting what practices we can without fully making the move (we still have much to learn before we can fully move on over!).
One of the things we want to implement now, before making the full switch, is the taskboard. We all feel it's a great tool that can help with development, and help keep those business users off our backs with the "what you doing?" and "how's it going?" questions and meetings.
So with all that said, one thing I've been wondering is can the tasks on the taskboard change? I know you don't want to be changing Stories, but what about tasks within a story? What if a new task came up, or an old task is no longer valid? Can they be added and/or removed mid-sprint (though we're not really using sprints, more like short development cycles).
Thanks!
I know you don't want to be changing Stories, but what about tasks within a story? What if a new task came up, or an old task is no longer valid? Can they be added and/or removed mid-sprint (...).
Yes, they can. During an iteration, a team typically gathers knowledge and gets a better understanding of what has to be done, or not. As a consequence, a team may discover that a task isn't really relevant, that a given Backlog Item requires more work than expected, that an initial estimation is wrong. In such cases, you definitely want to update your Sprint Backlog and the Burndown Chart to stick to the reality and keep what has to be done visible: you really want to know if the iteration is still on track, if you can take one more items, etc.
So, yes, don't hesitate to update, remove, add tasks as soon as you discover it has to be done. And the earlier, the better.
In our team, we use a task board inspired by Scrum and XP from the Trenches from Henrik Kniberg and we have a special location for "unplanned items" as illustrated below:
We like this approach because it makes easy to detect if unplanned items are killing an iteration. And we also "review" such tasks during the retrospective to see how we can improve our planning meeting, our estimations, the way we break down items, etc.
The team commit on user stories, not
tasks
It's not a problem to have some tasks changing as you are facing problems or have better implementation ideas.
In fact, it's very rare to finish a sprint with every task 100% "predicted" accurate in the sprint planning meeting.
They can and should change. The board should be updated at least daily.
But Pascal replied to that already - I want to make another point: from experience 'trying to adopt' Agile through small changes won't work. Scrum is a complete framework - by this I mean there is very little in Scrum (I'd say nothing) that can be dropped without doing harm to the process and promoting dysfunction or at least allow dysfunction to continue (wrote about it). Going slowly can be the only way to go in some companies/circumstances, but it has this risk that lingering dysfunctions will blow the process of change/improvement before it can reach its end and yield benefits.
I already like Pascal and Andy's answers so not to repeat.
A usefull alternative is to start a Kanban Board. Henrik Kniberg also has a good 'book' about it, available here:
http://blog.crisp.se/henrikkniberg/2009/04/03/1238795520000.html
It allows you to organise your work and be isert some Agile thinking into the company. As Andy said, Scrum is an All-in, if not you will find that 'It doesn't work'.
Why not? Leave the space to team to complete the work the way they would like to do.
Stories are 'contract' between client, product owner and team, therefore it is good to not change, add, remove stories without letting them know. But tasks are only for team.
The team should be able to track the effort the way they need to make it visible.
Questionable is a change of hours the team commited to complete in the sprint, but good scrum master and experienced team is able to self-organize that.

Agile - When does it work well, and when doesn't it? [closed]

Closed. This question is opinion-based. It is not currently accepting answers.
Want to improve this question? Update the question so it can be answered with facts and citations by editing this post.
Closed 5 years ago.
Improve this question
Our team is debating whether we want to become Agile or not. None of us are really fluent in Agile. I'd like some thoughts on when Agile works well, and when it doesn't.
To give a little background, we are a small group of developers, six in total. We have far more work that we can handle. Our priorities change often. What is a high priority today, may not be tomorrow. We have many applications to create and maintain. We have started to dabble in Agile practices to the extent that we have daily scrums and two-week Sprint cycles.
If you need more information to answer this, please feel free to ask.
Thanks.
Ralph Stacey's complexity matrix is commonly used to illustrate the sweet spot for Agile:
(source: typepad.com)
For simple projects (where both the requirements and the technologies are well known), the predictability is high so a predictive methodology (waterfall) works well.
For complicated and complex projects (and the vast majority of IT projects are), predictability is low and a predictive methodology won't work, an adaptive approach should be preferred. This is where Agile works well.
When both the requirements and the technologies are unknown, you're close to the chaos and the odds of failure are very high, regardless of the methodology.
I'm speaking only from experience; YMMV.
My team was unsuccessful at making agile work. IMO, it was because:
The very first time the dev team
would hear about a project, it was in
the form of a requirements document
and a deadline.
Stakeholders were often reluctant
to take time to look at the result
of a sprint's work, thus they would not take action between sprints if they thought the project was headed in the wrong direction.
When we showed stakeholders our work,
they generally just OK'd it. They
would talk about what they would
like, to which we would reply "That
can be done in about X amount of
time," to which they would reply,
"Well no need to go over the deadline
for that."
The deployment process was long and
complicated, discouraging frequent
deployments. So in practice, we
often deployed things when a 2-month
project was done, not at the end of a
sprint.
Our sprint planning meetings were
long and inefficient.
It seems everyone was confused about what scrum is (and about what our process was), except for the scrum evangelists.
So I'm pretty sure we were doing it all wrong. Don't you do it wrong, too.
Some things that have sped us up, which we continue to use:
automated builds that work on
everyone's machine (HUGE help!)
a formal arrangement for our code
repository
learning how to apply apply
abstraction mechanisms to UI code
refactoring
unit and integration tests
continuous integration
I guess you could say that our code is more agile, though our methodology is less agile. Whereas before we could not keep pace with demands, now we can.
(I'm not saying agile is bad; I'm just reporting my experience. Also, please understand that I do not choose what methodology we use.)
Reposting a related answer of mine:
The discussion is usually agile vs. waterfall, right? I am linking an article, but it is in Portuguese, so I'll try to transmit some of its ideas:
Waterfall is like chess. You think and plan a lot, try to foresee every possible issue as soon as possible. There's a lot of planning, but makes sense only on stable and well-known domains, where change isn't much expected.
Agile is like soccer (or many collective sports): decisions are made in-game and should be done fast. There's no much time to analyze every consequence. It is "ideal" for dynamic and unstable domains, where change is always expected (web applications, for instance, tend to fall in this category). Another point to note is: even if you have the best players, if they don't do well as a team, you won't be the winner.
IMHO, Scrum would be useful, because:
Once every two weeks (or every month, depending on iteration time) you'll be able to see what's working or not. And this is very valuable, specially as an "amateur" team, which is expected to be learning and finding things out much more constantly.
As amateurs, you probably won't be able to foresee everything (and that's something agile embraces)
There's more space for sharing experience (stand-up meeting, retrospective, and even planning meeting). And you share REAL experience (you must write code every week rather than just plan)
It appears your priorities are changing far too frequently for either methodology Agile or Waterfall. With priorities changing frequently, you are likely churning in and out of projects leaving a lot of them partly done. The Agile alway be ready to release may help. It has been my experience that getting a methodology in place will improve productivity.
Your situation reminds me of a project I worked on. The developer on the project asked one question at the start, "Do you want me to be do it right or be responsive?" I was on the project when it was two years into a six month project. One week the same functionality was implemented Monday, Wednesday, and Friday. Tuesday and Thursday were spent removing the functionality.
I would suggest you start adopting practices from Agile. Scheduling a short sprint period could help with changing priorites. It may be easier to maintain priorities for a period of a week or two and may make it easier to stabilize priorities. You will also need a backlog (sounds like you have a large one already).
Management may be more willing to hold off new priorities if you can slot them into a sprint in a week or two. You will also be able to identify the priority tradeoffs. If you add something to the next sprint, what will be removed.
Consider having part of the team working Agile while the others maintain the status quo. Rotate one team member each sprint as you are gaining experience. Consider having the whole team participate in a daily stand up status meeting, and the post sprint review. Once you have demonstrated increased productivity and returns to the company you should be able to increase the amount of work being done using your methodology.
Agile is a adaptive methology. Expect to be making major changes to your methodoly for the new year or two. Eventually, you should reach a stage where you are fine tuning.
In my experience, you absolutely need the following for agile (XP or Scrum at least) to work. Without these prerequisites you are likely to fail. Hard.
Team must be stable and 100% dedicated to this.
Team must be colocated in one workspace.
Customer/product owner must be available on site at all times.
Support from management. This means providing funds and courage to ensure the points above.
Give these points, you can probably tackle anything as long as you keep to the values.

What can a single developer learn from Scrum? [closed]

Closed. This question is opinion-based. It is not currently accepting answers.
Want to improve this question? Update the question so it can be answered with facts and citations by editing this post.
Closed 5 years ago.
Improve this question
Let's say that a developer is interested in learning Scrum, but nobody else on the team is interested. I realize that Scrum is made for teams, and the process would have to be modified to fit a single person.
Is there any benefit to be gained by the developer trying Scrum, even if the team doesn't? If so, how would the process be modified to suit the situation?
I think there's benefit to be gained by any method that helps you develop goals, tasks, keep on top of work and deliver something often.
Your individual work-products would gain the same advantages that teams gain with scrum:
You'd get something done every {Sprint Iteration Period Here}, something you can hand off and say "This is now ready".
Your estimation technique will start to improve with reflection and retrospectives
You'll start to plan your day and make commitments to yourself about getting things done, so again your estimation of your capacity will increase
Retrospectives will formalize improvement of your personal work process. You'll start actively improving, removing and adapting to suit you and your individual needs.
You wouldn't be able to rely on other team members to help out, which is a bit annoying, and you wouldn't have a product owner, Scrum master or a backlog to pick tasks from. You may not even be in a position to make decisions on what to work on next. But I think the formal discipline and reflection is helpful for all craft practitioners, at all levels, alone or in groups.
And who knows, you might even inspire your team to Scrum it up once they see what great results you're getting.
I would suggest that you use Extreme Programming instead, as that works better for one programming than a decidely team-based process.
Then you can get the benefits of being more agile, but if your team is not agile then you will have some issues due to the use of a different paradigm.
For me, the biggest key was getting buy-in from my supervisor. It can be tough to try and have some sort of Sprint only to have it interupted multiple times (Supposedly XP teams handle this better, but I don't think any developer does.). Also, don't forget to include either power users (they could be testers) or members of other departments that could be used as Product Owners. I like to sit with other users and do a type of paired programming (OK they don't code) where I can ask questions while coding and do quick demos to get feedback. This helps when I'm struggling to create specs because those requesting the app are having a hard time telling me what they want.
Even if it's just you in the daily stand-up, it can be scrum.
If you compare yesterday's planned with actual and define today's plans -- without talking to other people -- that's still a kind of daily stand-up.
I'd say that what you're doing probably is scrum if you're following the daily-sprint-release cycles; even if there aren't a any other people to talk to each morning.
G'day,
For the best thing to come out of learning Scrum is the concept of involving the customer early and often. That way there are no nasty "that's actually not what we wanted" moments when you deliver to the customer after six months hard work.
HTH
cheers,

How to educate a development manager about the difficulties of software design? [closed]

Closed. This question is opinion-based. It is not currently accepting answers.
Want to improve this question? Update the question so it can be answered with facts and citations by editing this post.
Closed 5 years ago.
Improve this question
I have had a few development managers who don't seem to understand or appreciate the difficulties of software design and implementation.
Such managers believe that processes and methodologies completely solve the problem and I have a tough time explaining to them that it is not so and that you cannot read a book on the latest process fad and hope to get results by applying them as is.
The latest frustration I have is to convince my manager to
(a) Give me requirements not piece-meal but a larger set as far as possible.
(b) Give my team lead time to think about how to design, thrash out a few alternatives, work out an implementation sketch, to plan out the tasks etc.
The frustrations are compounded because of Agile methodology and the interpretation of it that says not to do up-front design (as against BIG up-front design in Waterfall), product owner can change requirements at any time and so son.
So far I haven't had much success and have to put up with the resulting frustrations.
Can you give me some arguments that can convince such managers?
EDIT-1:
Retrospectives are done, though not always at the end of every sprint, and the problems are brought up. But as I mentioned, my manager doesn't appreciate the need for design lead time and the frustrations with piece-meal requirements.
EDIT-2
I don't have a problem with changing requirements. I understand that it will be so, but imagine this: You want a small feature to begin with and then you keep adding more around it. After a few iterations, the design cannot handle it anymore and a redesign (not refactoring) is required. This could have been solved better with an upfront design in the first place, had the related features been investigated together. Its not BDUF, its the natural way of doing it (what I call software engineering common sense).
My manager doesn't understand why I ask for time to redesign (a few times I just call it refactoring so that it fits the Agile way of doing it, but it really is redesign) and not developing and demoing new features.
Every time requirements are changed (or increased) so should
the estimate to complete and,
the assessment of risk
Start giving updated estimates (even if you have to guess) and lists of risks every time you get an updated or new requirement. This will help your manager make the connection.
Try to do this in a spirit of helpfulness--"for planning purposes"--so that you aren't perceived as obstructive or lacking "can-do attitude." Remember that estimates can (in theory) come down, and risks can be reduced.
Business requirements are going to change no matter where you work. It's not your fault, it's not your boss's fault, it's not anybody's fault. The entire point of taking the requirements on piecemeal is to encourage you to think about the problem at hand, not some other problem that you might or might not need to solve. It's quite liberating once you get into the rhythm of it.
Think of upfront design as premature optimization. You may not need it, and even if you know you need it, you'll know more about your design two weeks from now than you know about it today. It'll help you solve your engineering problem with the best possible knowledge about the state of your code.
That having been said, edg is absolutely right. When you add more requirements, the estimate changes. This isn't the fault of the developers or anyone else; more work means more work no matter how you square it. If your boss doesn't realize that adding requirements will result in a larger estimate for the project you need to explain to him that Agile isn't a magic bullet that allows you to add more features without paying anything for them.
Agile Simple Design doesn't mean don't do ANY design/architecture up front.
It means do the minimal design up front, so that you will not pay a horrible price for reasonable change requests.
Scott Ambler talks about Change Cases - http://www.agilemodeling.com/artifacts/changeCase.htm
James Coplien talks about Agile Architecture - http://www.infoq.com/presentations/Agile-Architecture-Is-Not-Fragile-Architecture-James-Coplien-Kevlin-Henney
http://blog.jaoo.dk/2009/03/04/handling-architecture-in-the-agile-world/
The art/craft in all of this is in how to slice the architecture in a way that allows:
relatively fast convergence on overall architecture/infrastructure - on the order of days per months of estimated development time.
developing "just enough" architecture/infrastructure per each feature/requirement
doing the right balance of preparations for the future compared to focus on the features of today.
Its important that your Product Owner is aware of all of this balancing act as well, and you work collaboratively. He should understand that if you disregard all thinking for the future, each change will be very costly. There is a price to be paid for flexibility.
Its btw very similar to investment in QA and test automation. You pay something now, that will pay off only after X times you test the code. if the code never changes it was a waste of effort. but everyone knows that most code changes...
Buy your manager this book. That's what I did, and it worked great :)
First of all this issue seems quite sensitive, so all I wrote below is just my personal opinion, and not necessarily a wise thing to do.
In my opinion you cannot make software if you do not know what problem it should solve. If requirements come in small parts that are too small to oversee the problem, then I would just fire questions about the parts that seem to be missing. Like: "okay so the software should do X, but does that also mean Y or otherwise maybe Z? Because if it is Y then ... but if it is Z then ..." Of course if the manager is in the middle of extracting the requirements then he cannot answer, but at least he knows that there are still open issues that influence development.
About no lead time for design: design and development are an iterative process that could go hand in hand. It is just how you name the thing. If the manager wants to see some code at the end of the day, okay then I would just use the first half of the day to design and the second half of the day to make some code based on that design. If the manager does not want to see the design, fine with me then I'll just show the code.

How does off-the-shelf software fit in with agile development? [closed]

Closed. This question is opinion-based. It is not currently accepting answers.
Want to improve this question? Update the question so it can be answered with facts and citations by editing this post.
Closed 5 years ago.
Improve this question
Maybe my understanding of agile development isn't as good as it should be, but I'm curious how an agile developer would potentially use off-the-shelf (OTS) software when the requirements and knowledge of what the final system should be are changing as rapidly as I understand them to (often after each iteration of development).
I see two situations that are of particular interest to me:
(1) An OTS system meets the initial set of requirements with little to no modification, other than potential integration into an existing system. However, within a few iterations of development, this system no longer meets the needs without rewriting the core code. The developers must choose to either spend additional time learning the core code behind this OTS software or throw it away and build from scratch. Either would have a drastic impact on development time and project cost.
(2) The initial needs are not like any existing OTS system available, however, in the end when the customer accepts the product, it ends up being much like existing solutions due to requirement additions and subtractions. If the developers had more requirements and spent more time working on them up front, this solution could have been used instead of building again. The project was delivered, but later and at a higher cost than necessary.
As a software engineer, part of my responsibilities (as I have been taught), are to deliver high-quality software to the customer on time at the lowest possible cost (among other things). Agile development allows for high-quality software, but in some cases, it might not be apparent that there are better alternatives until it is too late and too much money has been spent.
My questions are:
How does off-the-shelf software fit in with agile development?
How do the agile manager and agile developer deal with these cases?
What do the agile paradigms say about these cases?
Scenario1:
This can occur regardless off the OTS nature of the component. Agile does not mean near-sighted.. you'd need to know the big chunks.. the framework bits and spend thinking time on it beforehand. That said, you can only build to what you know .. Delay only till the last responsible moment.Then you need to pick one of the alternatives and start on it. (I'd Avoid third party application unless the cost of developing it in-house is infeasible.. but that's just me). Prototype multiple solutions to check feasibility with list of known requirements. Keep things loosely coupled (replacable), easy to change and full tested. If you reach the fork of keep hacking or rewrite, you'd need to think of which has better value for the business and pick that option. It's comes down 'Now that we're here, what's the best we can do now?'
Scenario2:
This can happen although the chances are slim compared to the team spending 2-3 months trying to get the requirements 'finalized' only to find that the market needs or customer minds have changed and 'Now we want it this way'. Once again, its a question of what is the point of time till which you are prepared to investigate and explore before committing on a path of action. Decide wisely with whatever information you have upto that point.. Hindsight is always 20-20 but the customers wont wait forever. You can't wait till the point of time where the requirements coalesce to fit a known OTS component :)
Agile says Do whatever makes sense and strip out the non-value-adding activities :) Agile is no magic bullet. just my 2 agile cents :)
Not a strict answer per se, but I think that using off the shelf software as a component in a software solution can be very beneficial if:
It's data is open, e.g. an open database or a web service to interact with it
The off the shelf system can customised easily using a similar programming paradigm to the rest of your solution
It can be seamlessly adapted to the rest of your work-flow
I'm a big fan of not re-inventing the wheel, and using your development skills to design the 'glue' between off-the-shelf solutions can be a big win.
Remember 'open' is the important part, and a vendor will often tout their solution as open when it isn't really.
I think I read somewhere that if during an iteration you discover that you have more than 20% more work that you initially thought then you should abandon the sprint and start planning a new one taking into account the additional work.
So this would mean replanning with the business to see if they still want to go ahead with the original requirements now that you know more.
At our company we also make use of prototyping before the sprint to try and identify these kind of situations before they arise on a sprint. Although of course that still may not identify the kind of situation that you describe.
C2 wiki discussion: http://c2.com/cgi/wiki?BuyDontBuild